Power Cost Estimator
Power to Land Cost Estimator
Get an idea for bringing power to vacant land, before you commit to a property.
Enter your land's details below. We'll show you the estimated cost of grid connection versus off-grid solar — side by side, including total cost over however long you plan to own.
0.5 miles
0
½ mi — typical tipping point
5 mi
10 years
1 yr
15 yrs
30 yrs
Here's What the Numbers Say
⚡
Grid Connection
✓ Lower total cost
Upfront cost
Est. monthly bill
Total over yrs
☀️
Off-Grid Solar
✓ Lower total cost
Upfront cost
After 30% federal tax credit
Est. monthly cost
$0 / mo
Total over yrs
Total cost over years
Grid
Solar
Solar bar reflects cost after 30% federal tax credit.
Grid extension costs based on National Rural Electric Cooperative Association (NRECA) data: $35,000–$50,000 per mile average for rural line extension. Calculator uses $42,500/mile (midpoint), adjusted by terrain: flat 1.0x, light cover 1.2x, rocky/steep 1.5x. Minimum $5,000 (service entrance). Solar system costs based on NREL and SEIA 2025 installed cost data for off-grid systems with battery storage. The 30% federal Investment Tax Credit (ITC) applies through 2032. Battery replacement every 8–12 years ($3,000–$8,000) is not included in solar total. Monthly grid bill estimates: Minimal $80/mo, Small cabin $120/mo, Full cabin $200/mo. These are estimates. Get written quotes from your local rural electric cooperative and a licensed solar installer before making any decision.
Get our weekly land inventory in your inbox.
Available properties, guides like this one, no spam. Unsubscribe any time.
Questions about a specific property? Call or text Andrew at (313) 349-0434
Browse Available LandDon't Wait
Your Land Is Out There
Properties move fast. Browse our current listings or call us directly -
we'll help you find land that fits your budget and your vision.